While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?

You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter.

What value should you report to management based on your project’s performance?

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project

Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly’s schedule performance index for this project?

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC

What type of communication method are you using in this instance?

You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes? A. Scope Verification B. Configuration

Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of

What can you do to rectify this problem?

You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated.

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen to the project duration?

You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will

Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?

Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance

Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your

What is the process in which Tom is working?

Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ultimate disposition of project

What is the schedule variance for this project that Fred needs to report to the management?

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the

What does it mean to crash the project?

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are

What is the review of the late work commonly called?

Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the

What must be true of these project activities for crashing to be acceptable?

Mary is the project manager for her company. She’s working with the project team to compress the project schedule as the project must be completed by December 30. For some

If Amy’s project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on

Management wants to know what the project’s cost performance index (CPI) is. What value do you report?

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be

What is this limit technically called? Each complete solution. Choose all that apply.

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project,

The consultant can best be described as what type of resource for this project?

You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each Answer represents a complete solution. Choose three.

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during

If Amy’s project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on

Management wants to know what the project’s cost performance index (CPI) is. What value do you report?

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be

What is this limit technically called? Each complete solution. Choose all that apply.

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project,

The consultant can best be described as what type of resource for this project?

You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire

Which of these does constructability take into account during analysis? Each Answer represents a complete solution. Choose three.

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during

Which one of the following is NOT an input to the Develop Schedule process?

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and

Which of the following individuals performs various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement?

Which of the following individuals performs various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement? A. Seller B. Operations

What is the schedule variance of your project?

You are the project manager of the OOI Project and you’re forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to

What project management process are you working with when you create a new target schedule?

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team

Which of the following is the best example of apportioned effort?

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of

Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the

Which organizational theory explains the factors that promote performance of people in any organization?

Which organizational theory explains the factors that promote performance of people in any organization? A. Herzberg’s theory B. Maslow’s Hierarchy theory C. McGregor’s theory D. Expectancy theory Answer: A

What type of an estimate are you creating in this scenario?

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately

Which tool and technique are you using in the define activities process in this scenario?

You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but

What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?

Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know

What will be the cost performance index (CPI) of the project at the current point of time?

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: Measurements

What is the estimate at completion for this project that Harry will need to report to management? A. $1,312,504

Harry works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty

Which of the following approaches will likely add costs to the project?

You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than

Who should Nancy deliver this final project report to if she is participating in a projectized structure?

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95.

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete

There have been some errors in the project which has caused you to spend $2,073,654. What is this project’s schedule performance index?

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete

What is the cost variance for this project that Fred needs to report to management?

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it? A. Scope

There have been some errors in the project, which has caused you to spend $2,073,654. What is this project’s schedule variance?

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete

You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channels for the project?

You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stakeholders

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard? A. It is a report that details the

Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?

Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance? A. Functional manager B. Operations

A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a person must have to be selected as a project manager?

A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a

Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?

Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer? A. Project