A project has been experiencing some difficulties due to third-party vendors. The project manager should request.

A project has been experiencing some difficulties due to third-party vendors. The project manager should request. A. Additional resources B. A gate review C. A risk register update D. A

A company is hired to perform some of another organization’s work. Which of the following types of organizational change is described?

A company is hired to perform some of another organization’s work. Which of the following types of organizational change is described? A. Outsourcing B. Business process change C. Shared resources

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying? A. Transfer B. Accept C. Avoid D. Mitigate

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success? A.

A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?

A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes? A. Quality

Which of the following documents should the project team reference to fast-track the project? (Choose two.)

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project

Which of the following is the BEST step for the project manager to take?

A senior manager asks a project manager for an estimated budget on a new project. Which of the following is the BEST step for the project manager to take? A.

Which of the following actions should the project manager take?

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the

Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?

Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule? A. Project manager and project scheduler

An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:

An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called: A. an RFP. B. an NDA.

Which of the following techniques is the project manager using?

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information? A. The project

Which of the following events would MOST likely trigger communications to the largest audience for a given organization?

Which of the following events would MOST likely trigger communications to the largest audience for a given organization? A. Business continuity response B. Quality audit C. Replacement of a subcontractor

Which of the following strategies should the project manager use to improve attendance? (Choose two.)

A project manager has noticed poor attendance as status meetings. Which of the following strategies should the project manager use to improve attendance? (Choose two.) A. Provide an agenda before

Which of the following is MOST likely to be the first document created by the project manager?

A vendor has accepted a proposed project from a customer. Which of the following is MOST likely to be the first document created by the project manager? A. Project charter

The project manager is concerned that the requests will lead to:

A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule. The project manager is concerned that the

Which of the following is the MOST expedient communication method, assuming the question can be resolved quickly?

A project team is composed of numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop

In which of the following organizational structures would a project manager have the MOST authority?

In which of the following organizational structures would a project manager have the MOST authority? A. Projectized B. Strong matrix C. Balanced matrix D. Functional Answer: A

Which of the following is the MOST likely reason?

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change. Which of the following

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well. The project manager should:

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the

Which of the following steps can the project manager take to make the meetings more productive?

Team members have reported that meetings are poorly attended and unproductive. Which of the following steps can the project manager take to make the meetings more productive? A. Discontinue the

Which of the following is a schedule that illustrates the duration of an activity?

Which of the following is a schedule that illustrates the duration of an activity? A. Process diagram B. Ishikawa diagram C. Gantt chart D. Pareto chart Answer: C

To alter the pace of the project, which of the following should the project manager do FIRST?

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the

Which of the following should the project manager do to resolve this issue?

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following

Which of the following effects is this MOST likely to have on the project?

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new

Which of the following documents should the project coordinator use?

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies. Which of the following documents should the project coordinator

Which of the following should have occurred to prevent this issue?

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their

Which of the following are critical for the project manager to provide?

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project. Which

In which of the following documents can this information be found?

A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found? A. Project schedule B. Cost plan

Which of the following are examples of organizational change? (Choose two.)

Which of the following are examples of organizational change? (Choose two.) A. Relocation B. Scope C. Business process D. Schedule E. Risk event Answer: AC

Which of the following describes how a project is related to a program?

Which of the following describes how a project is related to a program? A. A program is a combination of multiple projects. B. A program contains an element of the

Which of the following is a necessary step to record the actual durations?

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the

This action is known as which of the following?

A business has implemented a new online performance management tool that allows functional and project managers to rate employees online. This action is known as which of the following? A.

Which of the following strategies is the project manager applying?

A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional

Which of the following factors will MOST likely influence the communication methods used in the project?

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following

Which of the following should the project manager do NEXT?

A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager

Which of the following should be the project manager’s NEXT steps? (Choose two.)

A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager’s NEXT steps? (Choose two.) A. The project manager should

Which of the following would the project manager MOST likely do?

A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following

Which of the following is MOST likely to be the main challenge the influences this decision?

A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference. Which of the following is MOST

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project? A. Sales clerk B. Marketing representative C. Team lead

Which of the following documents should the project manager create?

A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project

Which of the following risk strategies should the project manager adopt?

A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success. Which of the following risk strategies

Which of the following is a definition of an RFP?

Which of the following is a definition of an RFP? A. A document sent to potential vendors to solicit a bid for a project. B. A document sent to potential

Which of the following describes risk mitigation?

Which of the following describes risk mitigation? A. The transfer of the risk to another entity or project inside or outside the organization, along with associated costs. B. The understanding

Which of the following is the BEST project management methodology for this requirement?

A customer will have ongoing changes to project requirements. Which of the following is the BEST project management methodology for this requirement? A. Waterfall B. Agile C. PRINCE2 D. Bottom-up

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project? A. EAC B. BAC C. TCPI D. ETC Answer:

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project? A. SOW B. PO C. SLA D. MOU Answer: A

Which of the following project documents should be used to record the occurrence of an unplanned event?

Which of the following project documents should be used to record the occurrence of an unplanned event? A. Action log B. Risk log C. Change log D. Issue log Answer:

Which of the following would be the BEST source for the high-level project requirements?

A new project charter is being drafted. Which of the following would be the BEST source for the high-level project requirements? A. Sponsor B. Project manager C. Project management office

Which of the following documents should be used to provide high-level reporting to key stakeholders?

Which of the following documents should be used to provide high-level reporting to key stakeholders? A. Dashboard B. Communication plan C. Statement of work D. Project charter Answer: A