An engineer must start a software upgrade on a Cisco Nexus 5000 Series Switch during a zone merge. What is the result of this action?
A. The upgrade stops
B. The zone merge pauses until the upgrade completes
C. The zone merge stops
D. The zone merge executes and then the upgrade completes
Correct Answer: A